Day 18 – Saturday 09/03/2019 – Offsite Reporting

Posted in Uncategorized | Leave a comment

Day 17 – Friday 08/03/2019

06:30 hours pre-start 07:00 hours calibration of air samplers 07:15 hour placement of air samplers adjacent to areas 1 and 2 07:20 hours inspection of liner on area 3 found to be satisfactory: 09:00 hours PM10s across site between 0.01 … Continue reading

Posted in Uncategorized | Leave a comment

Day 8 – Wednesday 27/02/2019

06:30 hours pre-start 07:00 hours placement of air sampler pumps A2, A3, A4, and A5 07:15 hours wind speed and direction: 0 to 1 m/s from ESE 07:30 hours placement of sprinkler(s) – dust suppression areas 1 and 2, and … Continue reading

Posted in Uncategorized | Leave a comment

Day 3 – Wednesday 20/02/2019

06:30 hours pre-start 06:50 wind speed 0 to 1 m/s WNW – PM10s across site less than 0.010 mg/m3. No significant downwind variations compared to upwind dust levels. 07:00 hours air samplers ID 08..11 at A2, A4, A6, A1 – … Continue reading

Posted in Uncategorized | Leave a comment

Day 1 – Monday 18/02/2019

10:30 hours pre-start site meeting of stakeholders 12:00 hours inspection of site by stakeholders 14:30 – 18:30 hours background air monitoring Maximum PM10 measured during work in progress: 0.024 mg/m3 – Results for PM10s measured are satisfactory i.e. consistent with … Continue reading

Posted in operations, Uncategorized | Tagged , | Leave a comment

Revised Start Date

SF: Based on the weather and flooding in Townsville and Richmond, work will not commence next week on the 11th Feb. I have contacted the client and Superintendent and suggested delaying 1 week, with a revised start date of Monday … Continue reading

Posted in Uncategorized | 1 Comment