Day 17 – Friday 08/03/2019

06:30 hours pre-start

07:00 hours calibration of air samplers

07:15 hour placement of air samplers adjacent to areas 1 and 2

07:20 hours inspection of liner on area 3 found to be satisfactory:

Area 3 – liner installed Friday the 8th March 2019

09:00 hours PM10s across site between 0.01 and 0.20 mg/m3 i.e. low dust levels.

Levels of dust upwind compatible to levels of dust downwind i.e. dust is not migrating offsite.

10:00 hours – area 6 liner being installed

Installation of liner – Area 6

NATA Certificate of Analysis >>